Krastel-Leideneck

2014

  • Rhineland-Palatinate, Rhein-Hunsrück-Kreis, Katellaun, Bell
  • 4 x E-101 / 135 m (3,05 MW)

Krastel-Leideneck Wind Farm

Since 2.9.2014, the first rotor in the Krastel-Leideneck wind farm has been turning. Then, at the beginning and end of October, the second and third turbines were added. The fourth turbine was connected to the grid on 31.10.2014.

Since then, our first wind farm with Enercon E-101 turbines was installed.

The electricity produced is fed into DunoAir’s own substation in Mastershausen.

Environmental balance

Estimated yield

26.6 million KWH

So2 Savings

13,570 tons

Co2 Savings

13,970 tons

Production

Electricity for 6,850 3-persons households